Question 152:
You want to move one of your leaf switches connecting to your ACI fabric to another rack. It will be reconnected to the same fabric after the move. Which operations must you perform before the move?
Answer options:
A. Decommission the switch and remove from the controller. B. Disable the interfaces. C. Blacklist the ports. D. Decommission the switch.