Question 69:
A network administrator wants to plan a major OS upgrade of the router, which acts as a default gateway in an organization. The administrator has documented the purpose of the change, scoped the change, and completed a comprehensive risk analysis. Which of the following is an important part of the change request process for which the administrator still must plan?
Answer options:
A. Inform management regarding the anticipated amount of downtime B. Document a backout plan to roll back changes to the router C. Configure a redundant data path to eliminate downtime D. Make the downtime window larger than actually anticipated