9 / 530

Question 9:

A company has completed construction of a new datacenter, and the IT staff is now planning to relocate all server and network equipment from the old site to the new site. Which of the following should the IT staff reference to determine the location of the equipment being moved? 

Answer options:

A. Rack diagrams
B. Network topology
C. Standard operating procedures
D. Wiring documentation