A project manager is attempting to establish the proper sequencing and duration of project activities. Which of the following would be the MOST beneficial?
Answer options:
A. Network diagram
B. Ishikawa diagram
C. WBS
D. Gantt chart
Answer correct:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 160