Question 104:

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast- tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference? 

Answer options:

A. MOU
B. MOA
C. SOW
D. SLA