Question 104:
An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast- tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?
Answer options:
A. MOU B. MOA C. SOW D. SLA