Question 112:

A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT? 

Answer options:

A. RF1
B. RFP
C. RFQ
D. Change request