Question 121:

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects: ✑ Coordinate project schedule ✑ Manage to the triple constraint ✑ Provide performance feedback to team members` managers Which of the following types of organizational structures did the new project manager MOST likely join? 

Answer options:

A. Balanced matrix
B. Strong matrix
C. Functional
D. Projectized