Question 133:
A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?
Answer options:
A. Submit a change request. B. Evaluate the impact of the change. C. Get approval from the CCB.D. Communicate the change to stakeholders.