Question 133:

A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT? 

Answer options:

A. Submit a change request.
B. Evaluate the impact of the change.
C. Get approval from the CCB.D. Communicate the change to stakeholders.