Question 136:
׀ new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review. Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
Answer options:
A. Identify and document the risk. B. Evaluate the impact and justification. C. Implement the change. D. Update the documents and plans.