Question 141:
A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?
Answer options:
A. Scope B. Time C. Quality D. Cost
Answer correct:
D
Reference: https://programsuccess.wordpress.com/2011/05/02/scope-time-and-cost-managing-the-triple-constraint/