Question 157:
A project manager is trying to explain to a stakeholder why projects are progressively elaborated upon. Which of the following is the BEST explanation?
Answer options:
A. In the beginning, projects entail a degree of uncertainty that needs to be specified. B. In the beginning, projects have start and finish dates that require elaboration. C. In the beginning, projects are part of a program that requires coordination. D. In the beginning, projects start with detailed inputs that need to be explained.