16 / 350

Question 16:

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder? 

Answer options:

A. Confidentiality
B. Criticality
C. Frequency
D. Cultural differences