Question 163:
A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 - PV = 80 - EV = 120 - Based on this information, the CPI reflects which of the following about the project?
Answer options:
A. It is under budget. B. It is over budget. C. It is ahead of schedule. D. It is behind schedule.