Question 168:
The business stakeholder has been engaged late and has just had a chance to review the approved requirements. Consequently, it has been identified that there are a number of gaps in the requirements which are critical to the stakeholders`s business unit. Which of the following actions should the project manager take?
Answer options:
A. Initiate change control. B. Follow communications plan. C. Manage project quality. D. Prepare a performance report.