Question 172:

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule compression techniques should be used by the project manager? 

Answer options:

A. Rescheduling
B. Crashing
C. Rebaselining
D. Control scope