Question 19:
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?
Answer options:
A. Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately. B. Evaluate the risk, fill in the issue log, and communicate it according to the communication plan. C. Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan. D. Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.