Question 211:

A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT? 

Answer options:

A. Revise the project plan.
B. Update the issue log.
C. Request additional funding.
D. Issue a change request.