Question 222:
Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed. Following are the durations of all tasks:
Which of the following tasks are on the critical path?
Answer options:
A. A, D, C, G B. A, B, H, G C. A, D, E, F D. A, B, C, G