Question 227:
A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to prevent scope creep?
Answer options:
A. Deny the CEO`s request. B. Implement the project change. C. Submit the request to the CCB.D. Ask the CEO to follow the communications plan.