Question 227:

A Chief Executive Officer (CEO) has approached a project team member to request a project change. Which of the following would be the BEST step for the project manager to take to prevent scope creep? 

Answer options:

A. Deny the CEO`s request.
B. Implement the project change.
C. Submit the request to the CCB.D. Ask the CEO to follow the communications plan.