Question 23:
The executive sponsor asks a project manager to summarize the following for a project: 1. Final capital expenditures. 2. Anticipated cost of new employee resources to support the solution. 3. Maintenance estimates. Which of the following information should the project manager provide?
Answer options:
A. Cost baseline B. Burn rate C. Cost variance report D. Total project cost