Question 239:
A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented: ✑ Project description ✑ Draft project timeline and schedule ✑ Rough milestones ✑ Draft project budget ✑ Draft resources required ✑ High-level risk review Which of the following sections should be included in this document?
Answer options:
A. Business information B. Full risk assessment results C. Draft work breakdown structure D. Full resource requirements