ExamQuestions.com

Register
Login
CompTIA Project+ Exam Questions

CompTIA

CompTIA Project+

26 / 350

Question 26:

A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. Which of the following techniques is MOST likely to be used to complete the project on time? 

Answer options:

A. Throttling
B. Crashing
C. Resource leveling
D. Resource smoothing