Question 264:
A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter: ✑ Project title description ✑ Preassigned resources ✑ Budget ✑ WBS ✑ Measurable project objectives Which of the following components should be a part of the project management plan instead of the project charter?
Answer options:
A. Project title and description B. Preassigned resources C. Budget D. WBS E. Measurable project objectives