Question 266:

A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as: 

Answer options:

A. change management
B. A milestone
C. a tollgate
D. an incident response