Question 268:

As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan. Which of the following documents should be reviewed FIRST to uncover the issue? 

Answer options:

A. Communications plan
B. Scope statement
C. Project management plan