Question 279:

A project manager is determining a project`s critical path to report the projected completion date to stakeholders. Which of the following information will be required? (Choose two.) 

Answer options:

A. Costs
B. Dependencies
C. Schedules
D. Durations
E. Holidays
F. Milestones