Question 29:
A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take?
Answer options:
A. Assess the risk register`s new items. B. Review the task start and finish dates. C. Obtain additional resources. D. Analyze the assigned hours.