Question 29:

A carpenter on a project team reports there is insufficient time to accomplish tasks on schedule. Which of the following is the FIRST step the project manager should take? 

Answer options:

A. Assess the risk register`s new items.
B. Review the task start and finish dates.
C. Obtain additional resources.
D. Analyze the assigned hours.