Question 293:
A client has requested a project be completed ahead of schedule. The client understands the triple constraints and agrees to expand the defect tolerance. Which of the following should the PM do NEXT?
Answer options:
A. Crash the schedule. B. Notify the project team. C. Initiate a change request. D. Accept the risk.