CompTIA Project+ Exam Questions

CompTIA

CompTIA Project+

318 / 350

Question 318:

Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns? 

Answer options:

A. Requirements
B. Lessons learned
C. Budget
D. Environment