Question 338:
Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
Answer options:
A. Determine the flexibility between the project constraints B. Hold a kick-off meeting with the project team C. Determine procurement needs to meet the project demands D. Create the risk register