Question 37:
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Answer options:
A. EAC B. BAC C. CPI D. ETC
Answer correct:
C
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231