Question 49:
Which of the following documents should be used to provide high-level reporting to key stakeholders?
Answer options:
A. Dashboard B. Communication plan C. Statement of work D. Project charter
Answer correct:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325