Question 51:
Which of the following project documents should be used to record the occurrence of an unplanned event?
Answer options:
A. Action log B. Risk log C. Change log D. Issue log
Answer correct:
D
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 327