Question 72:

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change. Which of the following is the MOST likely reason? 

Answer options:

A. Established communication plan
B. Scope creep
C. Resource constraints
D. Iterative approach