Question 82:
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
Answer options:
A. Project manager and project scheduler B. Project coordinator and project sponsor C. Project champion and project scheduler D. Project stakeholders and project team