Question 84:

A senior manager asks a project manager for an estimated budget on a new project. Which of the following is the BEST step for the project manager to take? 

Answer options:

A. Tell the senior manager the estimation is not available yet.
B. Use the budget from a similar project to generate estimates.
C. Ask a SME for an opinion and propose an estimate.
D. Gather the team to immediately generate estimates.