Question 88:
A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?
Answer options:
A. Transfer B. Accept C. Avoid D. Mitigate
Answer correct:
A
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238