Question 92:
A project has activities on the critical path that must be completed before other activities can start. Task A is dependent on Task C before Task D can be completed. Task A requires task B to start. Task B takes twice as long to complete as Task C. Which of the following is the appropriate ordering of the critical path?
Answer options:
A. B, A, D B. C, B, D, A C. D, A, C D. B, C, A, D