Question 145:
The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?
Answer options:
A. Ahead of schedule and over budget B. Behind schedule and under budget C. Ahead of schedule and under budget D. Behind schedule and over budget