Question 145:

The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status? 

Answer options:

A. Ahead of schedule and over budget
B. Behind schedule and under budget
C. Ahead of schedule and under budget
D. Behind schedule and over budget