Question 155:

A project team added a new member who has proprietary information about a competitor`s product. The team member was suddenly removed from the project. Which of the following MOST likely occurred? 

Answer options:

A. The company received a C&D.B. A higher-priority project needed the expertise.
C. The new member did not sign an NDA.D. An SLA prevented new team members.