The design activity of a project has the following cost attributes: PV = 100,000 - EV = 20,000 - AC = 90,000 - Based on this scenario, calculate the schedule variance.
Answer options:
A. -80,000 B. -70,000 C. 10,000 D. 120,000
Answer correct:
A