Question 185:

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected? 

Answer options:

A. Critical Path Method
B. Arrow Diagramming Method
C. Critical Chain Method
D. Precedence Diagramming Method