Question 225:
A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?
Answer options:
A. Description, cost difference of the replacement, and WBS B. Description, justification, and cost C. Cost difference of the replacement, justification, and communications plan D. Description, quality impact, and cost