Question 345:

A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM omitted? 

Answer options:

A. Identifying the risk
B. Obtaining approval from the CCB
C. Evaluating the impact of the risk
D. Communicating to stakeholders