Question 65:
A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?
Answer options:
A. Gain approval for the changes. B. Identify the approval authority. C. Implement the changes. D. Create an emergency change request.