Question 90:
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
Answer options:
A. Additional resources B. A gate review C. A risk register update D. A performance audit
Answer correct:
C
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 272