Question 279:
A technician is asked to install three servers: a 1U, a 4U, and a 6U. Which of the following is the MOST correct order to install these servers starting from the top of the rack?
Answer options:
A. 1U, 4U, 6U B. 4U, 1U, 6U C. 4U, 6U, 1U D. 6U, 4U, 1U