Question 143:
You and your project team are just starting the risk identification activities for a project that is scheduled to last for 18 months. Your project team has already identified a long list of risks that need to be analyzed. How often should you and the project team do risk identification?
Answer options:
A. At least once per month B. Several times until the project moves into execution C. It depends on how many risks are initially identified. D. Identify risks is an iterative process.