Question 178:
Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?
Answer options:
A. SV=EV-PV B. SV=EV/AC C. SV=PV-EV D. SV=EV/PV