Question 187:

You work as the project manager for Bluewell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decide, with your stakeholders` approval, to fast track the project work to get the project done faster. When you fast track the project, what is likely to increase? 

Answer options:

A. Human resource needs
B. Risks
C. Costs
D. Quality control concerns